After months of negotiations between the Basque and Spanish Governments, the Council of Ministers has approved the definitive version of the "Red de Transporte Horizonte 2030" Planning. This version incorporates the Basque Government's demands to increase Euskadi's electricity grid capacity by 50%, resulting in an increase of up to 6,000 MW.
This unprecedented investment will be transformative for industry, enabling its decarbonization, growth, and the attraction of strategic investments. To achieve this additional capacity, almost all existing substations will be upgraded, with over 20 actions planned, and 10 new substation parks will be created.
The planning will increase the capacity of the electricity grids by 6,000 MW to meet an additional demand of 2,300 MW in the transport network. This will be complemented by 3,000 MW of access capacity in the distribution networks, and over 750 MW of access capacity for renewable generation is also planned.
Mikel Jauregi, the Minister of Industry, Energy Transition and Sustainability, stated that "after many months of work, negotiation, and defense of Euskadi's interests, we have managed to agree with Madrid to increase our electrical capacity by 50%. We are responding to one of the biggest concerns of Basque industry: the lack of power outlets." He added that "in decarbonization alone, we are responding to 117 companies, guaranteeing more than 70,000 jobs in Euskadi."
These new investments, along with the approval of distribution network plans, create a transformative framework for Basque industry, green hydrogen production, the electrification of transport and ports, and the creation of new housing developments. The development and construction of new housing will be boosted, as some projects have been impacted by the lack of grid access.
The Minister concluded that "now it is time to accelerate and implement these investments as soon as possible," announcing a meeting next week with REDEIA, Iberdrola, and various institutions to commence the work.