The Vitoria-Gasteiz City Council has announced that energy renovation works at the Aldabe Civic Centre will begin in February and last for 18 months. This closure will allow the entire building to be adapted to fire safety and accessibility regulations. The centre will close to the public on 31 December, although the libraries will close on 19 December. Different services will begin operating in other locations from January.
The works will cost 6,143,271.66 euros (including VAT) and will be funded by European FEDER funds. The companies Geoxa and Emmepolis Novecento will carry out the works, which will focus on optimising heating and cooling systems to reduce primary non-renewable energy consumption by 45% and reduce maintenance.
“"That is the great strength of the civic centres, a network of fourteen facilities where some complement others when necessary."
Activities scheduled for the entire academic year, both cultural, sports and social, will be relocated to venues such as the El Campillo, Iparralde and Zabalgana civic centres, as well as the Landázuri and San Andrés sports complexes, the School of Arts and Crafts and the Errota ikastola. The Sports Service is informing clubs and entities about the relocation of their activities.
The basic social service will be based in Iparralde 2; the Citizen Attention service will expand its counters at the Iparralde office; the Information and Control staff will provide support at other centres; the Street Education programme will be relocated to Landázuri; the Meeting Room will reinforce the rooms at El Campillo, Iparralde and El Pilar; and the Library Service will be taken over by the rest of the network.
During the works, half of the civic centre car park will be closed for material storage and vehicle access will be modified for the 18 months of the works.