The Mungia City Council will undertake a comprehensive renovation of the sidewalk located next to number 1 San Pedro kalea. The primary objective of this initiative is to enhance safety and accessibility for pedestrians.
Due to wear and tear from time and usage, the existing tiles have become excessively slippery in certain sections. Responding to citizen needs, the council has decided to proceed with the sidewalk renewal.
The scope of work includes the demolition of the current pavement, earthmoving operations, and the construction of new foundations and surfaces. This project carries a total investment of 22,681.86 euros.
Work is expected to commence shortly, with an estimated duration of between two and three weeks.